Segmental block wall quantities: courses, blocks, caps, levelling pad, drainage stone and the geogrid layers that make a taller wall stand up. Enter the block dimensions from the product you are buying.

Walls above about 4 ft, walls carrying a slope or a surcharge, and any wall near a structure are engineered work. This tool counts materials for a layout; it does not check global stability, bearing or sliding. Get a design from a qualified engineer where one is required.
Bill of materials

Geogrid is what turns a stack of blocks into a reinforced soil mass: each layer ties the blocks back into the fill behind so the wall and the soil act together. Layer spacing and embedment length come from the design, not from the block, and they are the two numbers people guess at. The drainage stone matters just as much: a wall with no way to relieve water behind it is carrying hydrostatic pressure that it was never sized for, and that is what pushes walls over.

How to use this tool

Enter the wall length and exposed height with the block dimensions from the product you are buying, set the geogrid spacing and embedment from your design, and the tool returns courses, blocks, caps, levelling pad, drainage stone and total geogrid area.

It counts materials for a layout. It does not check stability, bearing or sliding, and walls above roughly 4 feet, walls carrying a slope or a surcharge, and walls near a structure are engineered work. Get a design where one is required.

Geogrid is what makes a tall wall work

A segmental wall is a stack of unmortared blocks. Below about 3 or 4 feet the mass of the blocks alone can resist the soil pushing on them. Above that, the soil wins, and the fix is not heavier blocks; it is to stop treating the wall and the soil as separate things.

Geogrid layers extend back from between the courses into the fill. Once the fill is compacted over them, the grid, the soil and the blocks act as a single reinforced mass, and the wall is effectively as deep as the grid is long rather than as deep as one block. This is why embedment length matters more than most people expect, and why cutting the grid short to save material undoes the entire mechanism. Spacing and embedment both come from the design, and they are the two figures people most often guess at.

The drainage stone is not optional

Water is the other thing that pushes walls over. Saturated soil behind a wall exerts far more pressure than the same soil drained, and the wall was never sized for it. The column of free draining stone behind the blocks, with an outlet at the base, is what keeps that pressure from developing in the first place. It is cheap, it is invisible once built, and it is the first thing omitted when a job runs tight, which is why so many failed walls look perfectly well built from the front.

A worked check you can repeat on paper

A 40 foot wall, 4 feet exposed, in 8 inch high by 12 inch long blocks. Courses are 4 times 12 divided by 8, which is 6. Blocks per course are 40 times 12 divided by 12, which is 40, so 240 blocks, plus 40 caps. With geogrid every 2 courses there are 2 layers below the top course, and at 4 feet of embedment that is 2 times 40 times 4, or 320 square feet of grid. Drainage stone 12 inches wide over the full 40 by 4 foot face is 160 cubic feet, or 5.93 cubic yards.

Section through a six course segmental block wall with geogrid layers extending back into the retained soil and a drainage stone column
Geogrid every two courses ties the blocks into the fill, so wall and soil act as one reinforced mass.

Mistakes that catch people out

Sizing the wall by eye above 4 feet. Fix: get an engineered design; this tool counts, it does not design.

Shortening the geogrid to save money. Embedment is the mechanism, not a margin. Fix: take the length from the design and enter it.

Omitting or blocking the drainage. Fix: the stone is a line in the takeoff and the outlet is part of the detail.

Forgetting buried courses. A wall is normally buried about a tenth of its height, so exposed height is not total height. Fix: enter the height you want counted and add the buried courses if your design calls for them.

How this was checked

The worked example was verified throughout: 6 courses, 40 blocks per course, 240 blocks, 40 caps, 2 geogrid layers totalling 320 square feet, 5.926 cubic yards of drainage stone and 1.481 cubic yards of levelling pad. The geogrid layer count was checked at the boundary so that no layer is placed above the top course, and block counts round up rather than leaving a partial block.